The Ministry of Defence has awarded almost 400 contracts worth roughly £3 billion since publishing its Defence Investment Plan, an average of about six a week, according to National Armaments Director Rupert Pearce. He gave the figures to the House of Commons Defence Committee while defending the department’s record on procurement speed and its engagement with industry.
Key facts
- Nearly 400 contracts, together worth about £3 billion, have been placed since the Defence Investment Plan was released.
- Commercial X, which mainly handles contracts of £50 million or less, has signed more than 1,200 contracts over two years.
- Its average time from first contact with a supplier to a signed contract is about 30 days, compared with roughly six years for major platforms.
- The MoD aims to grow its business with small and medium-sized enterprises (SMEs) by 50% by the end of 2028.
- The National Armaments Group has launched the first four of thirteen planned capability portfolios.
Background
The session followed weeks of criticism from industry that the Defence Investment Plan had not yet translated into a clear demand signal. Conservative MP Jesse Norman put that concern to Pearce, who replied that the department needed to move faster and bring industry further into the process, and that the delivery plan was being circulated to suppliers.
In an earlier one-off session on 20 October, representatives of ADS, techUK, the Federation of Small Businesses and Make UK told the committee that firms were holding back investment until they had greater certainty over contracts and programmes. The same panel praised Commercial X, with the Federation of Small Businesses calling it highly effective at getting contracts to smaller firms and urging wider use of its model.
Pearce described Commercial X as a “skunk works” for testing whether parts of defence procurement can be done differently. He said he did not have a figure for the average time from contract to delivery.
Wider capacity concerns have been raised elsewhere, with auditors warning that the UK Defence Investment Plan faces a capacity gap. Pressure on the budget is another factor, as the committee has heard that nuclear spending now approaches a quarter of the UK defence budget, limiting room for other programmes.
On small businesses, Pearce said MoD business with SMEs had fallen last year but had since recovered and was growing again. Norman suggested the Office for Small Business Growth lacked staff, capability and outreach, and Pearce accepted that this was a fair assessment. At the October session, industry witnesses said the office had four staff against 29 suggested as appropriate. Earlier in the year, Minister for Defence Readiness and Industry Luke Pollard committed the department to raising direct spending with SMEs by £2.5 billion by May 2028.
What it means
The contract numbers give the MoD a concrete measure of activity at a time when suppliers want proof that the investment plan is turning into orders. An average of about £7.5 million per award, however, suggests that much of the early activity involves smaller purchases rather than the large platform programmes that drive long-term industrial investment.
For industry, sharing the delivery plan could be the more significant step. Firms have consistently said that predictable pipelines matter more than headline totals when deciding whether to hire, expand facilities or commit capital.
The gap between a 30-day route for smaller deals and multi-year cycles for major equipment highlights the central challenge. Scaling the faster approach while strengthening support for SMEs will be key tests of whether the department can meet its own targets.
FAQ
How many contracts has the MoD placed under the Defence Investment Plan?
Rupert Pearce told MPs that nearly 400 contracts worth about £3 billion have been placed since the plan was published, equal to around six per week.
What is Commercial X?
It is an MoD procurement unit that trials faster ways of buying, mostly for contracts of £50 million or below. It has signed over 1,200 contracts in two years, averaging about 30 days from first contact to contract.
What is the MoD’s target for small businesses?
The department aims to increase its business with SMEs by 50% by the end of 2028, including a commitment to raise direct SME spending by £2.5 billion by May 2028.
Sources
Original reporting: UK Defence Journal (by George Allison), with additional reporting from UK Parliament Defence Committee oral evidence
Official source: House of Commons Defence Committee – oral evidence on the Defence Investment Plan and UK industry (20 October 2026)