The UK National Audit Office has warned that the Ministry of Defence has only limited assurance it can deliver everything set out in its £298 billion Defence Investment Plan. The spending watchdog’s findings point to significant capacity shortfalls in the organization responsible for buying and supporting military equipment, the UK Defence Journal reported.
Key facts
- The NAO assessed the affordability of the MoD’s £298 billion Defence Investment Plan (DIP).
- The National Armaments Director Group (NADG), which includes Defence Equipment & Support (DE&S), made £12.5 billion of adjustments to its four-year cost forecasts during the planning process.
- NADG reported an 18% shortfall against the capacity it needs and must reduce that gap to 10% to manage risk.
- About £1.4 billion of capital spending was deferred from 2026-27 and 2027-28 late in the process.
- The plan assumes around 20% of project costs will not be spent as scheduled, raising the risk of a spending “bow wave” after 2030.
Background
The Defence Investment Plan sets out how the MoD intends to fund equipment and infrastructure over the coming decade. DE&S, part of the National Armaments Director Group, manages much of the procurement and support work that the plan depends on.
According to the NAO, planned workforce reductions would make NADG’s capacity gap significantly worse. NADG told auditors it would face a choice between spending more on contractors in the short term or halting work on several important programmes, in addition to those already paused or cancelled through the DIP process.
The watchdog also said that when NADG agreed to defer £1.4 billion in capital spending, the department did not have a definitive set of measures showing how those savings would be achieved. The MoD told auditors that its planning had since matured.
Separately, the MoD has set a target to cut civil service costs by at least 10% by 2030. The NAO found emerging evidence that this was leading to some civil servants being replaced by military personnel, even though civil servants are generally cheaper to employ. In September 2025, then-minister Al Carns described the goal as a productivity ambition rather than a headcount target.
Gareth Davies, head of the NAO, said the MoD has taken important steps to improve its understanding of the plan’s costs but that much remains to be done. He said the department must now monitor the plan closely, maintain accurate cost information and be transparent with Parliament about emerging pressures.
What it means
For the UK defence industry, the findings signal uncertainty over the timing of some programmes. Deferred capital spending and the assumption that a fifth of project costs will slip suggest that contract awards and payments could shift to later years, concentrating demand after 2030.
The capacity shortfall within the procurement organization matters as much as the budget itself. Even when funding exists, a lack of skilled staff to run competitions, manage contracts and oversee delivery can slow programmes. The NAO highlighted munitions, the integration of uncrewed ships and aircraft with crewed platforms, and research and development as areas facing particular delivery challenges.
Parliamentary committees are likely to use the report to press the MoD on how it will close the capacity gap without either increasing contractor spending or stopping work on priority projects.
FAQ
What is the Defence Investment Plan?
It is the MoD’s £298 billion plan for funding military equipment and related investment, which the NAO says the department has only limited assurance it can fully deliver.
What is DE&S?
Defence Equipment & Support is the MoD organization that buys and supports equipment for the armed forces. It sits within the National Armaments Director Group.
What is the “bow wave” risk?
Because the plan assumes about 20% of project costs will not be spent on schedule, the NAO warns that deferred spending could build up and create higher costs after 2030.
Sources
Original reporting: UK Defence Journal (George Allison).